Albanna Engineering was the main contractor for Mechanical, Piping, Civil and E&I works for the Terminal Expansion Project.

The scope included detailed engineering, procurement, construction, testing, painting and commissioning of complete product piping system for the new tank farm. Civil works includes construction of new bridge, extension of existing bund wall, tank farm area grading and foundations.The scope also includes fire fighting works and E&I works.

Albanna Engineering has successfully executed this 12 month project in time up to the satisfaction of client.

Customer :STAR Energy Oil Tanking
Consultant : WS Atkins
Execution Period : 2009 - 2010
Piping : 24,000” Ø
Painting : 7,500 SqM
Internal Cement Lining : 1,950 SqM
Structure : 200 Tons
Concrere Works : 450 CuM